All Saints’ Roof Progress Report

The work on the roof is almost complete. Stonemasons have been working this week to repair and strengthen high level stonework on the nave and chancel. The rainwater goods are now being refurbished and repainted. The source of damp staining at the north east corner of the chancel has been identified and will soon be fixed.

The ceiling in the corner of the vestry above the boiler has been removed to find out the source of dampness there. Water has been gathering there for some time and caused some rotting of the timbers. These will need to be replaced from above, which will mean removing the zinc roof covering and then relaying it. A new flue lining will need to be fitted, the stonework made good, and the corner of the ceiling repaired.

We knew there was a problem in the vestry but it has turned out to be worse than expected. However, it is the only substantial problem we have met so far, and all the other work is at the moment proceeding on schedule. The construction industry is allowed to continue working through the lockdown, and our contractors are doing so, but we could still be affected by the pandemic.